Bills of materials and routings

The recipe and the steps: components, scrap, work centres and versions.

Baca dalam Bahasa Indonesia

On this page
  1. The bill of materials
  2. The routing
  3. Getting the master data right
  4. In Voltrus
  5. Checklist

In a spreadsheet factory, the recipe for a product lives in someone's head or in a tab called "komposisi" that nobody dares to sort. When the head of production is on leave, nobody knows exactly how much resin goes into a batch, and the cost sheet still uses last year's recipe.

An ERP holds two master records for every product you make: the bill of materials (what it is made of) and the routing (how it is made, step by step, and where). Planning, costing, material issue and labour reporting all read from these two records, so getting them right is the single most important set-up task in manufacturing.

The bill of materials

A bill of materials (BOM) lists the components and quantities needed to make one unit of a parent item, in the parent's base unit.

Parent: Cabinet C-200 (1 pcs)Qty perUnitScrap %
Side panel SP-102pcs0
Shelf SH-053pcs0
Steel sheet 0.8 mm1.5kg5
Screw M424pcs2
Powder coat0.2kg10

Three ideas you will meet in every ERP:

  • Levels. A component can have its own BOM. Here, Side panel SP-10 is itself made from steel sheet, so the cabinet's structure is two levels deep. When the system works out how much steel to buy, it explodes the BOM level by level, multiplying quantities as it goes; MRP nets each level against its own stock first, so side panels already on the shelf need no steel (see MRP).
  • Component scrap. Some material is always lost: cut-offs, overspray, rejects at the press. Scrap percentage on a BOM line inflates the requirement so planning orders enough. 1.5 kg of steel at 5% scrap means 1.575 kg is planned and issued per cabinet.
  • Units. The quantity per is in the unit shown on the line. If you buy steel in sheets but consume it in kg, a unit conversion on the item handles the translation; stock always moves in the item's base unit.

Process loss, co-products and by-products

Line scrap covers one component. Some processes lose part of everything that goes in: moisture boils off a batch of sauce, a rice mill's husk blows away. That is process loss, set once on the BOM as a percentage of the material put in. The work order quantity stays the good output; the components are planned at quantity ÷ (1 − loss). A sauce BOM of 1 kg of tomatoes per jar with 20% process loss plans 1.25 kg per jar, and issuing that much is normal, not over-consumption.

Many processes also make more than one product. A rice mill turns paddy into head rice, broken rice and bran:

OutputKindPer kg of riceHow it is costed
Head rice (the BOM item)main1what is left: 80% of the cost after the bran
Broken riceco-product0.25 kg20% of the cost after the bran
Branby-product0.5 kgfixed Rp 1,000 per kg, taken off the cost first
  • A co-product has real value of its own and takes an agreed share of the job cost (ERPNext and Odoo call it the cost share).
  • A by-product is incidental. It is valued at a fixed or standard value, and that value reduces the main product's cost.

If 2 kg of paddy at Rp 5,000 make 1 kg of rice, the job costs Rp 10,000; the bran is worth Rp 500, leaving Rp 9,500, of which broken rice takes 20% (Rp 1,900) and head rice keeps Rp 7,600.

Over-production tolerance belongs here too: how far above the work order quantity a batch may come out (a food batch that yields 2% more). It is set on the BOM, or on the item for all its BOMs.

Versions and the one active BOM

Recipes change: a cheaper screw, a new supplier's sheet thickness, a design fix. Rather than editing the BOM that past work orders were built from, you create a new version, check it, and activate it. The old version is retired but kept, so you can always see what a work order released last March was supposed to consume.

At any moment exactly one version is the active one. Planning, cost roll-up and new work orders use it. A work order fixes (pins) the BOM version at release, so activating a new version does not change work already on the floor.

Where-used

The reverse question matters just as much: "Screw M4 is being discontinued; which products use it?" A where-used lookup walks the active BOMs upward and lists every parent, directly or through sub-assemblies. Use it before changing or phasing out any component.

The routing

The routing lists the operations to make one unit, in sequence, each at a work centre:

SeqOperationWork centreSetup (min)Run (min / unit)
10Cut and punch sheetPRESS-1302.0
20BendBRAKE-1203.0
30Powder coatPAINT451.5
40Assemble and packASSY012.0
  • Setup time happens once per batch, whatever the quantity: changing dies, cleaning the spray booth.
  • Run time is per unit.
  • Queue time is the wait before an operation (parts cooling, a batch waiting for the oven); move time the wait after it before the next one can start. Neither costs labour, but both take calendar time, so scheduling counts them.
  • Sequences in steps of 10 leave room to insert an operation later without renumbering.

Work centres

A work centre is a machine, a line or a group of people that does an operation. It carries the rates that turn minutes into money:

  • Hourly (labour) rate: what an hour of this work centre costs in wages.
  • Overhead rate: the hourly share of electricity, depreciation, supervision and other indirect cost, often called machine burden.
  • Cost centre: which department's results its cost belongs to.
  • Capacity: hours per day of one machine, the days of the week it works, how many machines (or crews) work in parallel, and an efficiency percentage (at 80%, 60 planned minutes take 75 on the clock). A calendar of exceptions closes a centre for a maintenance shutdown or opens a Saturday shift; company holidays close every centre.

For the cabinet, a 50-unit batch at PRESS-1 takes 30 + 50 × 2 = 130 minutes. At a labour rate of Rp 60,000 per hour and overhead of Rp 90,000 per hour, that operation absorbs Rp 130,000 labour and Rp 195,000 overhead. The full calculation is in Product costing, WIP and variances.

Getting the master data right

The BOM and routing are only as good as the discipline around them:

  1. One owner. Engineering or production engineering owns BOMs and routings; nobody else activates a version.
  2. Measure, then set. Use real time studies or averages from past work orders for run times. Guesses produce a standard cost nobody believes.
  3. Every purchased component has a cost. A roll-up cannot cost a product whose screw has no price.
  4. Change by version. Never repair a BOM that past orders used; create the next version.
  5. Check after every change. Re-run the cost roll-up and look at the change in product cost before activating.

In Voltrus

What is not there yet, so plan around it:

  • No alternative work centres. Each step runs at the work centre the routing names; when it is overloaded, move the work order or change the routing.
  • No phantom or kit item types. Items are raw, finished or consumable. A sub-assembly that is never stocked still needs its own work order, or you flatten its components into the parent BOM.
  • No engineering change order (ECO) document. Use versions plus the record's Discussion tab to record why a change was made and who agreed to it.

Checklist

  • Every manufactured item has exactly one active BOM and one active routing.
  • Scrap is on BOM lines, not buried in quantities.
  • Work centre rates are set and reviewed at least yearly.
  • Every purchased component has a cost.
  • Changes go through a new version, with the reason written in the discussion.